Robotsan
Club Member
Just given the floors their first coat of epoxy 2k.
But I can't work out how long I have to wait until I can do a 2nd coat?
The tech sheet seems to only talk about handling time (5 hrs) and sanding time (18 hrs). I was assuming it'd be best to give it at least 24 hours, but from googling, some people seem to be saying it can be done after an hour or 2?
Link to data sheet: https://portal.lechler.eu/DesktopMo...oad.aspx?Command=Core_Download&EntryId=136093
But I can't work out how long I have to wait until I can do a 2nd coat?
The tech sheet seems to only talk about handling time (5 hrs) and sanding time (18 hrs). I was assuming it'd be best to give it at least 24 hours, but from googling, some people seem to be saying it can be done after an hour or 2?
Link to data sheet: https://portal.lechler.eu/DesktopMo...oad.aspx?Command=Core_Download&EntryId=136093